Adiabatic Nitration of Benzen goes on!

2. 3. 2021

The Adiabatic Nitration of Benzene project in Ostrava continues even under these climatic and emergency conditions!

Implementation date: 08/2020 - 06/2021

Industry: petrochemicals

Since January 2021, more intensive installation of pipeline routes and additional steel structures has started on the construction site.

Current progress

6,158 of the total 9,018 carbon steel inches (CS), i.e. 2,667 of 3,797 welds
13,412 of the total 21,381 stainless steel inches (alloy + SS), i.e. 5,012 of 8,954 welds

Continue to follow the development of this project!