Skid units for ZVU Engineering a.s., Czech Republic

18. 11. 2019

We are working on the project for ZVU Engineering a.s., pre-assembly and installation of
IN & OFF SKID piping and technological equipment for 30.000 Nm3 / h Hydrogen Plant.

Take a look at the pictures from the ongoing  project for ZVU Engineering a.s., pre-assembly and installation of IN & OFF SKID piping and technological equipment for 30.000 Nm3 / h Hydrogen Plant.

This is a pre-assembly of the pipe mat. class 11, 15 and 17 in the range of 190 000 kg, 18 pieces of skid units (steel structures) with a total weight of 106 700 kg and 12 pcs of technological equipment with a total weight of 5 433 kg placed in the skid units.

Start of the works August 26, 2019, finish by the end of February 2020.