We are currently cooperating on the project Adiabatic Nitration of Benzene implemented in Ostrava.

Industry branch: petrochemical

Quantity of piping 89 000Kg – 8 400 m

Used piping materials 1.0345 / 1.0255 / 1.4304 / 1.4404 / 1.4539 / 1.4541

Quality requirments: PED CAT II - 30%/CAT I - 10%

Prefabrication of supports 34 000 Kg

Current progress is 16 000 from 31 300 Inches welded on site, i.e. 6 200 from 12 800 welds.

Works in progress: 30 % implemented

Realization time 08/2020 -> 06/2021.

Follow the progress of this project in coming months ...